Poland

The Group, in conjunction with the local company Kobylarnia, signed a contract on April 3, 2013, regarding the completion of construction work of the A1 "Torun – Strykow" section of A1 highway, composed of 2 lots and about 64 km long, connecting the cities of Czerniewice and Kowal.

The project has a total value of approximately €255 million.

Work on the first lot was completed on May 23, 2014; the Taking Over Certificate was issued on December 4, 2014.

Work on the second lot was completed on July 23, 2014, and the Taking Over Certificate is dated December 19, 2014.

The percentage of completion as of December 31, 2014 was 100.0%.

The initiative, led by the Polish General Directorate of Roads and Highways and co-funded by the European Union, constitutes full implementation of the strategic agreement signed with the Group in September 2012.