The Plant segment order backlog at 31 December 2013 is as follows:
| Area/Country (In milions of euro) | Project | Residual backlog at 31 December 2013 | Percentage of total | Percentage of progress (%) |
|---|---|---|---|---|
| Fisia Italimpianti | ||||
| Middle East | Jebel Ali L2 | 2.4 | 1% | 98.8% |
| Middle East | Ras Abu Fontas B2 | 3.3 | 1% | 98.3% |
| Middle East | Jebel Ali M | 7.8 | 3% | 99.0% |
| Middle East | Jebel Ali M – ricambi | 8.5 | 3% | 1.9% |
| Middle East | Ras Abu Fontas A1 | 2.9 | 1% | 99.1% |
| Middle East | Shuaiba North | 2.2 | 1% | 99.4% |
| Middle East | Shuaiba North – ricambi | 9.2 | 3% | 50.6% |
| Middle East | Takreer Cbdc | 11.0 | 4% | 46.1% |
| Total Fisia Italimpianti | 47.3 | 15% | ||
| Fisia Babcock | ||||
| Germany | Datteln REA | 2.1 | 1% | 94.0% |
| Germany | Moorburg – ESP | 1.6 | 1% | 96.0% |
| Germany | Manheim Block 9 RRA | 12.2 | 4% | 85.0% |
| Netherlands | Maasvlakte Block 3 REA | 1.1 | 0% | 97.0% |
| Turkey | Yildizlar Orta FGD | 1.1 | 0% | 17.0% |
| Panama | Paco – FGD | 3.7 | 1% | 74.0% |
| Poland | Plock FGD | 36.5 | 12% | 7.0% |
| United Arab Emirates | Takreer – SWFGD | 5.1 | 2% | 19.0% |
| Other Abroad | 1.0 | 0% | n.a. | |
| Fume treatment | 64.4 | 21% | ||
| Russia | Moskau WtE | 92.5 | 30% | 18.0% |
| Germany | Ruhleben Wte | 1.6 | 1% | 98.6% |
| Germany | Wuppertal K 13 EfW | 1.9 | 1% | 92.0% |
| Switzerland | Linköping EfW | 49.7 | 16% | 4.0% |
| Finland | Tampere EfW | 33.0 | 11% | 5.0% |
| China | Haidian EfW | 8.3 | 3% | 43.0% |
| China | Hefei 3/4 EfW | 5.3 | 2% | 4.0% |
| Italy | 0.2 | 0% | n.a. | |
| Other Abroad | 1.4 | 0% | n.a. | |
| Waste to energy | 193.9 | 63% | ||
| Italy | 0.1 | 0% | n.a. | |
| Abroad | 3.7 | 1% | n.a. | |
| Other | 3.8 | 1% | ||
| Total Fisia Babcock | 262.1 | 85% | ||
| Totale engineering & plant construction | 309.4 | 100% |