Nigeria

Work on the "Gurara Dam and Water Transfer Project, Lot A – Dam and Associated Works" project is in the completion phase. The current value of the contract, including the various contractual additions issued over the years (the contract was signed on January 30, 2001) comes to about €622 million. The 9 million m3 earth and rockfill dam, intake works, and 30-MW hydroelectric plant are complete; the power transmission line, the irrigation perimeter, and some road work still need to be completed.

The percentage of completion as of December 31, 2014 was 97.9%.

Work is continuing on the "Development of Idu Industrial Area Engineering Infrastructure" contract (valued of approximately €251 million), consisting of the primary urban development works in a new district of the capital Abuja, intended for industrial use. The sewer and drainage networks are complete, 60% of the road network, including 4 viaducts, is paved, and construction is starting on the water supply and power supply grids.

The percentage of completion as of December 31, 2014 was 73.9%.

Work on designing and building the "Nigeria Cultural Centre and Millennium Tower" is also progressing (contract value of approximately €409 million). The tower structure has reached its final height of 170 m, the sails have been completed and the restaurant and glazing are nearly finished. The underground parking garage beneath the square has been completed, the tunnel linking the two plots of the project is complete, and the structures of the 7 buildings that make up the Cultural Centre and the Auditorium are at an advanced stage of construction. The steel covering of the auditorium has been finished. At the date of preparation of this Report, the installation of the multifunctional station and the planning setup remained still to do.

The percentage of completion as of December 31, 2014 was 36.6%.

The urban highway stretch of the "Extension of Inner Southern Expressway (ISEX)" for a value of roughly €70 million by the Federal Capital Development Authority with a contract signed on January 13, 2010, is in an advanced stage of construction. So far, 3 of the 4 major bridges have been completed, the drainage works are nearly finished, and most of the road is paved. The road lighting has also been installed.

The percentage of completion as of December 31, 2014 was 91.9%.

The "Dualization of Suleja Minna Road in Niger State", a contract obtained in November 2010 with a value of approximately €55 million, is under way. The earthwork and drainage works are currently in the completion phase, paving is partially completed and construction of all five bridges in the project has been completed.

The percentage of completion as of December 31, 2014 was 81.1%.

The "Development of District 1 Abuja North Phase IV West" project, worth a total of about €227 million, is ongoing. The bidding process was conducted in two phases (phase 1 – December 30, 2010, and phase 2 – March 5, 2012). Construction of one of the main bridges of the project is complete and the remaining culvert boxes of quadrant 1 have been made. In the same quadrant, the earth-moving and underground works (drainage and sewerage) are being finalized.

The percentage of completion as of December 31, 2014 was 12.6%.

On September 12, 2012, the "Adiyan Waterworks Phase II" project worth €232 million was acquired. This project consists of the design and construction of a water treatment plant with a capacity of 320,000 m3/day, intended to meet a portion of the Lagos population’s water needs. The civil works on the treatment plant are at an advanced phase of construction. The civil works for the intake structure from the river and the conduit are yet to be started.

The percentage of completion as of December 31, 2014 was 25.9%.